Philip.Skeet Philip.Skeet is offline Master Projects with different Working Days Windows 7 64bit Master Projects with different Working Days Office 2007
Novice
Master Projects with different Working Days
 
Join Date: Aug 2011
Posts: 1
Philip.Skeet is on a distinguished road
Default Master Projects with different Working Days

Hi Guys,
I was wondering whether MS Project 2010 has the ability to include multiple sub projects within a master project all with separate scheduled working weeks/times.
I have set some of the projects up as individual projects (7d working week & 24 hr day ops) and they are fine, however once I import them they are being transferred into the default standard working week of 8 hrs/d & 5 days/week.



Can anyone shed any light on this?

Cheers

Phil
Reply With Quote
  #2  
Old 08-19-2011, 07:31 AM
OTPM OTPM is offline Master Projects with different Working Days Windows 7 32bit Master Projects with different Working Days Office 2010 32bit
Expert
 
Join Date: Apr 2011
Location: West Midlands
Posts: 981
OTPM is on a distinguished road
Default

Hi Phil
You would need to setup a different calendar in your Master Project File for each sub project and then assign the relevant calendar to each sub project.
Hope that helps.
Good luck.
Tony(OTPM)
Reply With Quote
  #3  
Old 08-19-2011, 09:45 AM
Kimberly Kimberly is offline Master Projects with different Working Days Windows 7 64bit Master Projects with different Working Days Office 2010 64bit
Expert
 
Join Date: May 2010
Posts: 517
Kimberly is on a distinguished road
Default

If you INSERT instead of IMPORT the subprojects, they will only be links to the real project plans, and will retain their original calendars.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Merging Projects C_Howard Project 2 03-29-2012 02:00 PM
Master Projects with different Working Days Non-Working Days on Gantt JayTT Project 1 01-28-2011 05:42 AM
Linking tasks between projects error clear2pay Project 0 12-05-2010 06:46 PM
How do i implement learnings from completed projects? stingy Project 0 03-18-2010 02:09 AM
Writing code with C# and VB.NET to create Outlook add-ins and other projects kistou Outlook 0 01-13-2010 04:23 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 12:51 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft