viv_2_k viv_2_k is offline Links to several milestones on same line of a Gantt chart Windows 7 32bit Links to several milestones on same line of a Gantt chart Office 2007
Novice
Links to several milestones on same line of a Gantt chart
 
Join Date: Aug 2011
Posts: 2
viv_2_k is on a distinguished road
Default Links to several milestones on same line of a Gantt chart


I've plotted 4 milestones on the same line by using the rollup options to roll the subtasks to the summary and then collapsing the sub-tasks view. But by doing so, the predecessor dependency links disappear if I have to print chart. Is it possible to have the dependency links to point to their respective milestones on the summary bar itself?

Thanks
Reply With Quote
  #2  
Old 08-03-2011, 01:05 AM
OTPM OTPM is offline Links to several milestones on same line of a Gantt chart Windows 7 32bit Links to several milestones on same line of a Gantt chart Office 2010 32bit
Expert
 
Join Date: Apr 2011
Location: West Midlands
Posts: 981
OTPM is on a distinguished road
Default

Hi
You can have dependency links on a Summary task, however it is not good practice to do so as it would be unclear which of the child tasks the dependency actually applies to.
If you are using Project 2010 you can actually copy selective tasks to a Timeline chart which may give you what you want.
Hope this helps.
Tony(OTPM)
Reply With Quote
  #3  
Old 08-03-2011, 01:58 AM
viv_2_k viv_2_k is offline Links to several milestones on same line of a Gantt chart Windows 7 32bit Links to several milestones on same line of a Gantt chart Office 2007
Novice
Links to several milestones on same line of a Gantt chart
 
Join Date: Aug 2011
Posts: 2
viv_2_k is on a distinguished road
Default

Thanks Tony. I am using Project 2007. Can I do what you suggested with that version and if yes, how?

The reason why I grouped my milestones as sub-tasks and used roll-up is just for display purposes so that I can get all of them on one line. But if there is any other way to 'draw' 4 milestones on a single line and have the links pointing to each of them, please let me know.

Sorry for the basic questions. It's my first time using Microsoft Project and I am just using it to draw a good gantt chart, but not actually managing the project with it.. at least not yet.
Reply With Quote
  #4  
Old 08-03-2011, 04:40 AM
OTPM OTPM is offline Links to several milestones on same line of a Gantt chart Windows 7 32bit Links to several milestones on same line of a Gantt chart Office 2010 32bit
Expert
 
Join Date: Apr 2011
Location: West Midlands
Posts: 981
OTPM is on a distinguished road
Default

Hi Viv
Unfortunately that functionality is not available in 2007. However if you are happy to post a copy of your plan with instructions on what you want to achieve I will take a look and post some instructions back to you.
Tony (OTPM)
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Exporting Gantt Chart to MS Word 2007 earweed Project 4 06-02-2011 09:21 AM
Updating Excel Chart Links fermat PowerPoint 0 07-09-2010 04:29 PM
Custom animating a line chart by series and category. Gahzi PowerPoint 0 05-19-2009 11:53 AM
Links to several milestones on same line of a Gantt chart Gantt Chart: MS Project vs. Excel Nance Project 2 12-09-2008 01:59 PM
Links to several milestones on same line of a Gantt chart Page breaks inserted in Gantt chart have no effect Steve Sells Project 2 11-09-2005 08:12 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:12 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft