OTPM OTPM is offline Task Start and End Dates Windows 7 32bit Task Start and End Dates Office 2010 32bit
Expert
Task Start and End Dates
 
Join Date: Apr 2011
Location: West Midlands
Posts: 981
OTPM is on a distinguished road
Default Task Start and End Dates

Hi
I am using Project 2010 and cannot understand why if a task starts at 0900hrs on a Monday and is a five day task, the finish date is showing as 0900hrs the following Monday rather than 1700 hrs on the previous Friday!
I am using an eight hour day calendar.
Can anyone help.
Tony(OTPM)
Reply With Quote
  #2  
Old 11-10-2011, 04:34 AM
anarita anarita is offline Task Start and End Dates Windows 7 32bit Task Start and End Dates Office 2010 32bit
Novice
 
Join Date: Nov 2011
Posts: 1
anarita is on a distinguished road
Default

Hi, I have exactly the same problem. Have you figured how to solve it?
Reply With Quote
  #3  
Old 12-04-2011, 09:14 AM
JulieS JulieS is offline Task Start and End Dates Windows 7 64bit Task Start and End Dates Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Hi anarita,

What is the definition of a "day" in File > Options, Schedule? There are three places you need to ensure things are in synch:
**Project calendar - the default working time in the Standard Calendar is 08:00 - 12:00 and 13:00 to 17:00. If your working time is something other than that -- you need to modify the calendar for every working day through the Change Working Time command on the Project tab.
**Default start, default end, hours per day and hours per week setting in File > Options, Schedule.
**Resource calendar definitions - each resource has a calendar which is based upon another calendar. If the resource's calendar is different, this can also cause task dates and times to shift.

My guess is that you have a task which starts at 09:00 on Monday set a duration of 5 days (which equals 40 hours). Add 40 hours to 09:00 on Monday and you get 09:00 on the following Monday. You have started 1 hour into the working day (08:00 - 17:00) so the one hour you've missed on Monday morning has to be continued to the following Monday morning from 08:00 to 09:00.

I hope this helps.

Julie
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
start-stop month dates in calendar madison320 Project 0 06-24-2011 08:15 AM
Task Start and End Dates Calculating dates Daria11 Word VBA 1 06-08-2011 06:54 PM
Task Start and End Dates displaying start and finish times as absolute numbers instead of dates benson.wallace Project 2 12-05-2010 07:22 AM
how to make the task starts next day if no time enough today(task can not be split) duraid Project 1 10-25-2010 08:31 AM
Task Start and End Dates Setting Drop Dead Start Dates greenboard Project 2 06-14-2010 08:12 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:36 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft