Old 05-13-2011, 02:28 PM
stct stct is offline Finish Variance in Resouce Usage View Windows XP Finish Variance in Resouce Usage View Office 2003
Novice
Finish Variance in Resouce Usage View
 
Join Date: May 2011
Posts: 12
stct is on a distinguished road
Default Finish Variance in Resouce Usage View

Hi all,

Is there a way we can display a Task level column in 'Resource Usage view' with following formula:

Finish Variance = [ Baseline Finish Date (Task) - Finish Date (Task) ]

Custom field could be an option, but did not give the correct results. I would prefer to use non-custom (stock) field, if possible.



Pls advise,

Best Regards.
Reply With Quote
  #2  
Old 05-17-2011, 07:37 AM
OTPM OTPM is offline Finish Variance in Resouce Usage View Windows 7 32bit Finish Variance in Resouce Usage View Office 2010 32bit
Expert
 
Join Date: Apr 2011
Location: West Midlands
Posts: 981
OTPM is on a distinguished road
Default

Hi stct
I dont believe you can use task fields in a resource view and vice versa.
What are you trying to achieve?
I have used two custom date fields to put both dates in then used a custom number field to subtract one from the other and it worked fine.
When you say the result was incorrect bear in mind that Project also used hours and minutes in the date. So you will invariably get a result to two decimal places.
Hope this helps.
Tony
Reply With Quote
  #3  
Old 05-17-2011, 08:36 AM
stct stct is offline Finish Variance in Resouce Usage View Windows XP Finish Variance in Resouce Usage View Office 2003
Novice
Finish Variance in Resouce Usage View
 
Join Date: May 2011
Posts: 12
stct is on a distinguished road
Default

Hi Tony,

I am trying to create a view that will display Resource assignment and any task level variance (Ahead / Slippage # of days). This will help in discussing weekly review with the resource managers to prioritize workload.

I tried following steps:

a. Created 2 custom Resource level Date fields, with field value formulas (1) BaselineStart & (2) Start respectively.

b. Created a custom Resource level Number field, with field value formula (difference of above created custom date fields).

I inserted the custom number field in Resource Usage view and unfortunately, getting 0 value. I have attached sample project with this changes.

Pls advise,

Thanks in avance,
Attached Files
File Type: zip TaskVarianceResourceUsageView.zip (26.8 KB, 13 views)
Reply With Quote
  #4  
Old 05-17-2011, 02:07 PM
OTPM OTPM is offline Finish Variance in Resouce Usage View Windows 7 32bit Finish Variance in Resouce Usage View Office 2010 32bit
Expert
 
Join Date: Apr 2011
Location: West Midlands
Posts: 981
OTPM is on a distinguished road
Default

Hi
First of all dates are assigned to a task not a resource. This is why it will not work.
You can do what you want using the task view and put a formula in a custom field.
You could also consider using the "Status" column which will indicate whether or not a task is running late.
Hope this helps.
Tony
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Send e-mail message in Finish & Merge CDTom Mail Merge 1 08-24-2012 12:52 AM
Automatic resouce assignment of remaining unallocated units philk Project 0 05-04-2011 04:57 PM
Resource Usage sheet - options Andy Bain Project 1 11-05-2010 12:42 PM
Accessing Assignment Detail Data in Task Usage View CGM3 Project 0 10-05-2010 05:56 AM
Finish Variance in Resouce Usage View Help with Interim Baseline Variance poyns Project 1 05-27-2010 10:59 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 07:18 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft