Hello All
I am using Project 2007. I want to add the field "Cumulative Percent (%) Complete" to the time-phased portion of the "Task Usage" view. However when I right-click in the time-phased portion of the view the field is not available to add. Can anyone advise what I am doing wrong and point me in the right direction.
Any help would be appreciated.
Kind regards
TKHussar
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
how to make the task starts next day if no time enough today(task can not be split) duraid Project 1 10-25-2010 08:31 AM
How to refer a field in another field DaveSmith Word 0 08-24-2010 06:44 PM
Can't find Task Folder kc300c Outlook 0 08-02-2010 09:22 PM
Cannot Find a Task-timephased field can Find/Replace NOT find something? Bobosmite Word 6 05-27-2010 08:09 PM
Task Problem scotthutchings Outlook 0 07-03-2006 05:08 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:20 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft