#1
|
|||
|
|||
Resource Calendars
Hi,
I have created a new base calendar which I would like to use for all resources working on a particular project. However, although I have assigned my new base calendar to the project, my resources are still using the Standard calendar. I know that it is possible change the resource calendars one by one in the resource sheet view, but is there anyway to assign a calendar as a default calendar for all existing and future tasks and resources in the project. Thanks Caz |