Hi,



I have created a new base calendar which I would like to use for all resources working on a particular project. However, although I have assigned my new base calendar to the project, my resources are still using the Standard calendar.

I know that it is possible change the resource calendars one by one in the resource sheet view, but is there anyway to assign a calendar as a default calendar for all existing and future tasks and resources in the project.

Thanks
Caz
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Resource use on tasks Proj03 Project 0 01-24-2011 01:40 PM
MS Project Resource Chart fherbert PowerPoint 0 09-09-2010 12:20 PM
Using MSP to predict staff resource jarvo273 Project 0 05-13-2010 04:05 AM
Check out the Enterprise resource Sridhar Project 0 02-17-2010 09:52 PM
Resource Calendars Best training resource? (excel) wartrace Office 2 01-10-2010 01:09 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 10:38 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft