Hey all, new to the forum and Project.



We are using Project 2003 and I have the following problem.

I copied a pre-existing project from another member which had some holidays identified on the base calendar.
I made a copy of the base calendar and called it something else.
I added the rest of the holidays for the rest of the year to this new calendar (Tools - Change Working Time - Clicked Non Workingwtim button).
When I scroll throught the calendar, the days are displayed as 'nonworking'.
I have verified I am using the calendar in my project (Project - Project Information - Calendar: box indicates same name as above calendar).

Here's the problem - The Gantt Chart does not display my added holidays as non-working days.....however, the hoidays that were put in before are depicted via shaded bar.

Any thoughts?

Thanks,
Jay
Reply With Quote
  #2  
Old 01-28-2011, 05:42 AM
JayTT JayTT is offline Non-Working Days on Gantt Windows XP Non-Working Days on Gantt Office 2003
Novice
Non-Working Days on Gantt
 
Join Date: Jan 2011
Posts: 2
JayTT is on a distinguished road
Default

Never mind....stumbled across solution.
Apparently you have to go to <Format - Timescale> Click on "Non-working time" and select the correct calendar (even thought the calendar is already selected for the project).

Why would a user be required to apply the desired calendar in multiple choices (Project Information and now here) is beyond me.

Jay

Also just saw you can righ-click in the Gantt area and select "non-working time".
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Conditional formatting of Today +21 days? SHERMAN Excel 3 12-20-2010 08:08 AM
gantt bars with text and i'm losing the bar when i print oompa_l Project 0 11-17-2010 01:16 PM
Outlook Calendar continually resets days in Day View tecsi Outlook 0 08-11-2010 06:45 PM
Non-Working Days on Gantt Gantt Chart: MS Project vs. Excel Nance Project 2 12-09-2008 01:59 PM
Non-Working Days on Gantt Page breaks inserted in Gantt chart have no effect Steve Sells Project 2 11-09-2005 08:12 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:22 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft