Different % complete in Project Center & View a Project
 
Join Date: Dec 2005
Posts: 1
mikaelbelchior
Default Different % complete in Project Center & View a Project

Scenario:
- A MS Project is published on Project Web Access (PWA).
- After opening the project in MS Project and altering the field manually, the % complete field is changed.
- The project is re-published.

Problem:
The project % complete field is different in the PWA Project Center in comparison to the View a Project screen (or to the project in MS Project).



This is a serious problem, as with a number of our projects, the field % complete is underestimated in the Project Center. Consequently, stakeholders assume that less work has been done on the projects in comparison to what has actually been done.

How can this be corrected and avoided?
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Need some basic help on Project NewToProject Project 0 04-06-2008 07:03 AM
Error 9571 when opening Project Server from Project Pro mona Project 0 04-24-2007 07:50 AM
Project Server 2003 SP2 Project 15 01-25-2007 03:52 AM
Creating new project Using PDS myanilkumar Project 0 01-05-2006 12:35 AM
Help: MS Project viewer obenix Office 2 05-06-2005 01:28 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:37 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft