Hi all,
Does anyone know how to customise the Early Start, Early Finish, Late Start and Late Finish fields so that in the columns they display as they number of days/weeks/months since the project began. In other words, suppose I haven't decided on a start date for the project yet, but what I'm interested in seeing is the total number of days/weeks/months needed to complete the project. If the above is possible, then my follow-on question is - how does one change the network diagram so that it displays the Late Start and Late Finish fields as well? Thanks, Benson |
|
![]() |
||||