#1
|
|||
|
|||
Ressource planning incorrect with deactivated tasks
Hi,
I have an issue with my ressource planning. Altough I have deactivated some tasks with essources behind in the Gantt view the related ressources are listed in the ressource overview. This is randomly - some are listed and some not. Are you having any idea how this can be solved? Please see the screenshot attached. Any support is appreciated! Thanks Markus |
#2
|
|||
|
|||
Inactive tasks display automatically in the Resource Usage view. If you do not want to see Inactive tasks, insert the Active column and then AutoFilter for only the Yes values. Hope this helps.
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Change language in Project planning | massimodfd | Project | 0 | 04-26-2023 08:50 AM |
Planning A MS Word Job | William647 | Word | 6 | 11-13-2019 03:06 PM |
Event planning | cajos | Project | 3 | 03-26-2016 05:19 PM |
Project Status and Late Tasks - Incorrect | BarryB | Project | 4 | 08-02-2015 01:50 PM |
Finish to Start Tasks dates incorrect | Rowey | Project | 5 | 05-01-2015 07:22 AM |