Old 01-15-2024, 01:24 AM
hansfrap hansfrap is offline How to Link Bar-Style to Task-type Windows 11 How to Link Bar-Style to Task-type Office 2021
Novice
How to Link Bar-Style to Task-type
 
Join Date: Aug 2022
Posts: 11
hansfrap is on a distinguished road
Default How to Link Bar-Style to Task-type

In Project, tasks in the graphics area are formatted according to the defined bar style.
It is possible to manually adjust the color of the bar.

Question:
Is there a way to define a separate task that directly gives its own color in the graphic area?

For example: I create a special Task: Waiting, is it possible to show the bar style directly in the color I have predefined in Beam Style Formatting?
Reply With Quote
  #2  
Old 01-15-2024, 10:09 AM
DaleHowardMVP DaleHowardMVP is offline How to Link Bar-Style to Task-type Windows 10 How to Link Bar-Style to Task-type Office 2021
Advanced Beginner
 
Join Date: Apr 2023
Posts: 53
DaleHowardMVP is on a distinguished road
Default

Double-click the Gantt bar and then change the color in the Format Bar dialog.
Reply With Quote
  #3  
Old 01-17-2024, 06:44 AM
hansfrap hansfrap is offline How to Link Bar-Style to Task-type Windows 11 How to Link Bar-Style to Task-type Office 2021
Novice
How to Link Bar-Style to Task-type
 
Join Date: Aug 2022
Posts: 11
hansfrap is on a distinguished road
Default

@ Dale Howard
Thanks for an answer, but the question is whether there is a standard way to get a different color of the bar for a certain task.

Your proposal is to adjust the task afterwards, the question was to be able to define this in advance.

So I see the answer as placing buckets near a leaky faucet, instead of fixing the faucet.
Reply With Quote
  #4  
Old 01-17-2024, 09:43 AM
DaleHowardMVP DaleHowardMVP is offline How to Link Bar-Style to Task-type Windows 10 How to Link Bar-Style to Task-type Office 2021
Advanced Beginner
 
Join Date: Apr 2023
Posts: 53
DaleHowardMVP is on a distinguished road
Default

OK, I understand. Take a look at the "Create a new type of Gantt bar" section of the following Help article:

Format the bar chart of a Gantt Chart view - Microsoft Support

Create a custom task Flag field and give it a name of your choice. Insert this Flag field in any Task view and set a Yes value for tasks where you want a different Gantt bar color automatically. Then refer to the steps in the Help article to make this work. For example, I just automatically formatted a Gantt bar color using the dark Orange color when I entered a Yes value in the Flag1 field for a task, so I know this approach will work for you. Hope this helps.
Reply With Quote
  #5  
Old 01-17-2024, 12:18 PM
hansfrap hansfrap is offline How to Link Bar-Style to Task-type Windows 11 How to Link Bar-Style to Task-type Office 2021
Novice
How to Link Bar-Style to Task-type
 
Join Date: Aug 2022
Posts: 11
hansfrap is on a distinguished road
Default

Yes this is working!
Thank you for this tip.
Reply With Quote
  #6  
Old 01-17-2024, 01:57 PM
DaleHowardMVP DaleHowardMVP is offline How to Link Bar-Style to Task-type Windows 10 How to Link Bar-Style to Task-type Office 2021
Advanced Beginner
 
Join Date: Apr 2023
Posts: 53
DaleHowardMVP is on a distinguished road
Default

You are more than welcome for the help, my friend!
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
ms project 2019 - network diagram - link (arrow) from summary task to task wongpmw Project 1 05-28-2022 04:57 AM
How to Link Bar-Style to Task-type Style Type in Header Zach Greig Word 2 04-03-2016 01:07 PM
Task link help Tarkara Project 1 06-08-2015 09:02 AM
changing style type eNGiNe Word 1 03-01-2012 01:36 AM
Task type relationships not acting as expected Rkramkowski Project 0 12-08-2005 10:40 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:48 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft