artmusicstudio2 artmusicstudio2 is offline Szenario in Project? Windows 10 Szenario in Project? Office 2019
Novice
Szenario in Project?
 
Join Date: Mar 2021
Posts: 7
artmusicstudio2 is on a distinguished road
Default Szenario in Project?

hello,


i just switched from project 2000 to latest office365 version.

my biggest hope was to find a way to save different settings for the vieport like
- compact view
- view level 2
- view only selected , rest collapsed


but i cannot find it .

is there a function like this hidden somewhere deeper in the frontend?

i normaly print a compact version and some user versions und would like to have them "1 click" - print-ready.

(otherwise vba may help here ? )


thanx for any idea :-)

stan
Reply With Quote
  #2  
Old 01-29-2024, 07:11 AM
DaleHowardMVP DaleHowardMVP is offline Szenario in Project? Windows 10 Szenario in Project? Office 2021
Advanced Beginner
 
Join Date: Apr 2023
Posts: 53
DaleHowardMVP is on a distinguished road
Default

In Microsoft Project, a View is defined as a Table plus a Filter plus a Group plus a Screen. the Table is the set of columns you want to see. The Filter displays only the rows you want to see. The Group organizes rows into Groups with similar attributes or characteristics. The Screen is the graphical based image displays on the right side of the View, such as a Gantt Chart screen or a Task Usage screen.

To create the views you have described, you would need to create a custom Table for each View, and you might need to create a custom Filter for some of the Views. To learn how to create a custom View, you might want to watch one of my recent YouTube videos on this subject:

https://youtu.be/uf1cZC-fKnw

Hope this helps.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Project not updating task when project start date changed Nextenso Project 3 07-08-2023 11:55 AM
Reports created in Project 2016 not viewable in Project 2010 Murali Narayanan Project 0 05-23-2019 03:59 PM
How to modify the Gantt chart bar styles (label of values) in project center (WPA) (MS Project 2010) Cedahlia Project 0 04-21-2018 10:29 PM
Project task numbering changed after linking item in subproject to m aster project rrs_2017 Project 0 09-06-2017 06:07 AM
Microsoft Project Server, Microsoft Project Online and Project Web App - Whats the difference? chocolateCupcakes Project 1 02-11-2017 12:25 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:48 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft