Old 07-08-2023, 04:40 AM
Nextenso Nextenso is offline Project not updating task when project start date changed Windows 10 Project not updating task when project start date changed Office 2021
Novice
Project not updating task when project start date changed
 
Join Date: Jul 2023
Posts: 4
Nextenso is on a distinguished road
Default Project not updating task when project start date changed

Haven't used Project Desktop (via Office 365) for abt 18 months. Previously if I changed the Project Start Date, with all tasks set with precedent tasks it would update all the task dates respecting the new start date and the precedents' end dates and fully update the path timeline.



Now, in a new Project file, when I changed the Project Start Date to 28 days later with all tasks having precedents, it left all the tasks set at the dates unchanged, I am having to go to each task and manually set the task's start date 1 day after the end date of its predecessor. I tried removing the precedent task and re-applying, but Project will now not respect the date of the precedent task

All tasks are set to Auto Schedule, the task Constraint Type is set to the default 'as soon as possible' with Constraint Date as 'n/a'. I have tried different combos of Constraint Type and Constraint Date, it makes no difference.

I tried in Options/Schedule unticking and again then ticking the "Task will always honour...." That made no diff.

BUT, if I go to a task where I have not yet set a task date and apply a precedent, the precedent task end date is respected.

So, any task that already has a date set for it will not respect precedent task end dates since I changed the Project Start Date

Is there a change in the current version that stops what I used to see happen ???? Or have I forgotten to do something ????
Reply With Quote
  #2  
Old 07-08-2023, 07:29 AM
Nextenso Nextenso is offline Project not updating task when project start date changed Windows 10 Project not updating task when project start date changed Office 2021
Novice
Project not updating task when project start date changed
 
Join Date: Jul 2023
Posts: 4
Nextenso is on a distinguished road
Default added info

This is a project in planning stage, no tasks have been started, preliminary works delays caused the estimated start date to move back 1 month
Reply With Quote
  #3  
Old 07-08-2023, 10:35 AM
DaleHowardMVP DaleHowardMVP is offline Project not updating task when project start date changed Windows 10 Project not updating task when project start date changed Office 2021
Advanced Beginner
 
Join Date: Apr 2023
Posts: 49
DaleHowardMVP is on a distinguished road
Default

What happens if you use the Move Project feature instead of changing the Start date? You will find the Move Project button in the Schedule section of the Project ribbon. Let us know and we will try to help you.
Reply With Quote
  #4  
Old 07-08-2023, 11:55 AM
DaleHowardMVP DaleHowardMVP is offline Project not updating task when project start date changed Windows 10 Project not updating task when project start date changed Office 2021
Advanced Beginner
 
Join Date: Apr 2023
Posts: 49
DaleHowardMVP is on a distinguished road
Default

Ignore this reply

Last edited by DaleHowardMVP; 07-08-2023 at 12:01 PM. Reason: Answered wrong question
Reply With Quote
Reply

Tags
project start date



Similar Threads
Thread Thread Starter Forum Replies Last Post
Project task numbering changed after linking item in subproject to m aster project rrs_2017 Project 0 09-06-2017 06:07 AM
Project not updating task when project start date changed What are the implications of changing project start date raminraiszadeh Project 3 02-11-2015 03:13 PM
Project not updating task when project start date changed summary task calculating from project start ketanco Project 1 01-02-2012 02:34 PM
Project not updating task when project start date changed Groups to be sorted by start date in MS Project Antares Project 3 12-09-2011 03:17 PM
Project not updating task when project start date changed Project start date steve138 Project 4 05-20-2011 04:55 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:16 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft