#1
|
|||
|
|||
Resource Histogram
Hi guys, I hope you´re doing great.
Question: Is there any way to get a resource histogram, based on the resource assignment loaded in the resource sheet of a project file? I would like to build a resource histogram that shows the amount of resources required by day, according to the resource assignment on the resource sheet. This is with the idea of compare the amount of people available on work site, with the amount of resources declared in the project resource sheet. Thank you so much for the help you can give me related with this issue. Best regards, Alberto Villanueva. |
#2
|
|||
|
|||
Have you looked at the Resource Graph view in your project? That might meet your resource histogram needs. Let us know and we will try to help.
|
Tags |
resource histogram |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
How to plot a histogram on excel with relative frequency density | Aredo19 | Excel | 1 | 11-19-2020 11:07 PM |
Problems with vba frequency distribution histogram | leeqiang | Excel Programming | 19 | 09-01-2020 08:54 PM |
how to draw the histogram? | leeqiang | Excel Programming | 1 | 08-27-2020 05:19 PM |
Resource Reports not showing Sub project Resource group hours | RichB | Project | 3 | 02-24-2017 08:55 AM |
Resource Usage View - Is it possible to display resource names | Andrea Schanz | Project | 6 | 09-22-2014 07:47 AM |