Fixed Production Rate Scheduling
 
Join Date: May 2023
Posts: 1
AP1210 is on a distinguished road
Default Fixed Production Rate Scheduling

Scenario: I have a contract to install 100 widgets and I have a machine (resource) that installs 10 widgets per day. I want to be able to show 100 widgets that need to be installed, and when I assign the 10 widget per day resource, MS Project will automatically return a duration of 10 days. And if I change the quantity to 110 widgets, MSP will adjust the duration, or if I add a 2nd widget installer with a fixed production rate, the duration will adjust.
Is this possible? It seems like it should be a basic element...
Reply With Quote
  #2  
Old 05-30-2023, 03:27 PM
DaleHowardMVP DaleHowardMVP is offline Fixed Production Rate Scheduling Windows 10 Fixed Production Rate Scheduling Office 2021
Advanced Beginner
 
Join Date: Apr 2023
Posts: 46
DaleHowardMVP is on a distinguished road
Default

In Microsoft Project, Material resources can either be consumed at a Fixed Rate or a Variable Rate. What you need is to assign the Widgets at a Variable Rate. Set the Duration of the task to 10 days and assign the Widget resource at a rate of 10/day. Microsoft Project will then calculate the consumption at 100 widgets. If the Duration is increased to 15 days, the consumption will be 150 widgets.

In Microsoft Project, the software DOES NOT calculate the Duration of the task based on the consumption rate of the Material resource. It works the other way around. Hope this helps.
Reply With Quote
Reply

Tags
fixed production, schedule

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
How to create a Man Hour Resource with fixed durations and fixed Work jayreb31 Project 0 07-03-2019 01:14 PM
Fixed Production Rate Scheduling newb - need help automating catalogue production Deeper Office 2 09-09-2015 01:45 AM
Fixed Production Rate Scheduling Fixed duration, fixed units, fixed work, effort driven. How, why and when use it all Evgeny Project 3 01-03-2013 06:45 AM
Fixed Production Rate Scheduling How to use fixed duration, fixed work and have resources/units leveled automatically? Joeb Project 3 06-25-2012 04:18 PM
Fixed Production Rate Scheduling photo plate production phycobob Drawing and Graphics 1 02-15-2012 09:37 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 11:19 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft