#1
|
|||
|
|||
Setting resources without splitting the task
Hi, let me explain my problem with an example I have a task which takes 5 weeks and 500% resources to be done. How can i set this task to take 10 weeks using 300% resource in first 5 weeks and then 200% resource in next 5 weeks? I don't want to split this into 2 tasks (ie. part 1, part 2) Thank you in advance |
#2
|
|||
|
|||
Create the task and enter a Duration value of 10w. Assign the resource to the task at a Units value of 300%. Set the Task Type for this task to Fixed Duration to "lock" the Duration value of 10w. Apply the Task Usage view and zoom the timephased grid to the Weeks level of zoom. In the timephased grid, you should see 120h of Work assigned to this resource each week over the 10-week time span of the task. Starting in week #6, change the Work value to 80h for each week from weeks #6-10. Voila! That's how to do it. Hope this helps.
|
#3
|
|||
|
|||
Quote:
But still, GREAT JOB!! |
#4
|
|||
|
|||
Such a nice comment. Thanks for the kind thoughts!
|
Tags |
resource allocation |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Splitting a task which have sub tasks | djnegh | Project | 1 | 09-03-2015 07:44 AM |
Multiple resources on one task | joday48 | Project | 2 | 08-01-2014 08:56 AM |
Allocating multiple resources to a task and splitting the hours | pptdgc | Project | 1 | 07-22-2014 03:45 AM |
How to set task to be done by 4 resources each one after another? | lukusm | Project | 1 | 01-16-2012 07:21 AM |
Setting up resources | icw | Project | 2 | 09-04-2011 03:55 AM |