Setting resources without splitting the task
 
Join Date: May 2023
Posts: 1
tomtrk86 is on a distinguished road
Default Setting resources without splitting the task

Hi, let me explain my problem with an example
I have a task which takes 5 weeks and 500% resources to be done.

How can i set this task to take 10 weeks using 300% resource in first 5 weeks and then 200% resource in next 5 weeks?


I don't want to split this into 2 tasks (ie. part 1, part 2)
Thank you in advance
Reply With Quote
  #2  
Old 05-31-2023, 08:03 AM
DaleHowardMVP DaleHowardMVP is offline Setting resources without splitting the task Windows 10 Setting resources without splitting the task Office 2021
Advanced Beginner
 
Join Date: Apr 2023
Posts: 46
DaleHowardMVP is on a distinguished road
Default

Create the task and enter a Duration value of 10w. Assign the resource to the task at a Units value of 300%. Set the Task Type for this task to Fixed Duration to "lock" the Duration value of 10w. Apply the Task Usage view and zoom the timephased grid to the Weeks level of zoom. In the timephased grid, you should see 120h of Work assigned to this resource each week over the 10-week time span of the task. Starting in week #6, change the Work value to 80h for each week from weeks #6-10. Voila! That's how to do it. Hope this helps.
Reply With Quote
  #3  
Old 06-12-2023, 07:57 AM
psytek psytek is offline Setting resources without splitting the task Windows 10 Setting resources without splitting the task Office 2016
Novice
 
Join Date: Apr 2023
Location: Poland
Posts: 1
psytek is on a distinguished road
Default

Quote:
Originally Posted by DaleHowardMVP View Post
Create the task and enter a Duration value of 10w. Assign the resource to the task at a Units value of 300%. Set the Task Type for this task to Fixed Duration to "lock" the Duration value of 10w. Apply the Task Usage view and zoom the timephased grid to the Weeks level of zoom. In the timephased grid, you should see 120h of Work assigned to this resource each week over the 10-week time span of the task. Starting in week #6, change the Work value to 80h for each week from weeks #6-10. Voila! That's how to do it. Hope this helps.
Great explanation, I find myself as advanced user. I believe that slower "step by step" explanation would work well for all beginners.

But still, GREAT JOB!!
Reply With Quote
  #4  
Old 06-12-2023, 11:22 AM
DaleHowardMVP DaleHowardMVP is offline Setting resources without splitting the task Windows 10 Setting resources without splitting the task Office 2021
Advanced Beginner
 
Join Date: Apr 2023
Posts: 46
DaleHowardMVP is on a distinguished road
Default

Such a nice comment. Thanks for the kind thoughts!
Reply With Quote
Reply

Tags
resource allocation

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Splitting a task which have sub tasks djnegh Project 1 09-03-2015 07:44 AM
Multiple resources on one task joday48 Project 2 08-01-2014 08:56 AM
Setting resources without splitting the task Allocating multiple resources to a task and splitting the hours pptdgc Project 1 07-22-2014 03:45 AM
Setting resources without splitting the task How to set task to be done by 4 resources each one after another? lukusm Project 1 01-16-2012 07:21 AM
Setting resources without splitting the task Setting up resources icw Project 2 09-04-2011 03:55 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:05 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft