![]() |
#1
|
|||
|
|||
![]()
Hi!
I'm setting up a project with two resources added two the task - Work and material. I'm trying to create a report that shows the cost and usage ie: I would like a report showing the cost and usage/units per summary task... HOW? |
#2
|
|||
|
|||
![]()
If by usage/units, you are referring to the Units value for each of the assigned Work resources, then no, this information will NOT roll up to summary tasks. Cost and Work will roll up to summary tasks, however. Hope this helps.
|
![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Custom cost (Cost1) fields to timephased view in Task Usage | jp02145 | Project | 0 | 06-17-2019 06:42 AM |
![]() |
Rowena | Project | 3 | 05-30-2016 04:24 PM |
![]() |
pascalbidouille | Project | 1 | 08-21-2015 01:25 PM |
![]() |
Andrea Schanz | Project | 6 | 09-22-2014 07:47 AM |
Resource Usage view does not correctly export to a Visual Report | cergon | Project | 3 | 04-25-2014 06:10 AM |