how to make the task starts next day if no time enough today(task can not be split)
hi all i have a problem through my planification in MS Project
lets say that a have a task starts just before the end of the working day and the task can not be siplit so i want the task to start at the next morning (not at the end of day) can any one help me with this? |
#2
|
|||
|
|||
You can set a predessor task that uses a Night Shift calendar. This phony task can just be a minute long or whatever.
|
|