jraward jraward is offline Any way to display the portion of a task that is split by non-working time in a different colour? Windows 7 64bit Any way to display the portion of a task that is split by non-working time in a different colour? Office 2016
Novice
Any way to display the portion of a task that is split by non-working time in a different colour?
 
Join Date: Mar 2019
Posts: 2
jraward is on a distinguished road
Default Any way to display the portion of a task that is split by non-working time in a different colour?



Is this possible to do automatically? I need to illustrate that the task isn't 16 weeks long (like the first image), it's 12 weeks with a 4wk break driven by the non-working time (red shading) which I've mocked up in the second image.

The task may also move, but the non-working time won't (which is specific to this task).



I know I can manually split the task (which I've shown in the 3rd image) however when the programme changes that split will move from the non-working time and I need to manually drag it around.
Reply With Quote
  #2  
Old 04-21-2023, 08:06 PM
ineeju ineeju is offline Any way to display the portion of a task that is split by non-working time in a different colour? Windows 10 Any way to display the portion of a task that is split by non-working time in a different colour? Office 2021
Novice
 
Join Date: Jul 2022
Location: Seoul
Posts: 9
ineeju is on a distinguished road
Default

While it is possible to change the color of non-working time, it seems that not all tasks can be automated.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Any way to display the portion of a task that is split by non-working time in a different colour? Do not split task on task level Mattias Project 5 02-17-2017 09:36 AM
Any way to display the portion of a task that is split by non-working time in a different colour? Creating a task similar to Working Time exceptions jaywizz1 Project 1 11-04-2016 10:30 AM
Any way to display the portion of a task that is split by non-working time in a different colour? Employee Turnover by Department/Month split between Voluntary/Involuntary - Full-time/Part-time CPSmith Excel 1 03-26-2016 02:48 AM
Any way to display the portion of a task that is split by non-working time in a different colour? Remove time portion in date angie.chang Excel 4 06-13-2012 09:45 AM
how to make the task starts next day if no time enough today(task can not be split) duraid Project 1 10-25-2010 08:31 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:49 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft