benzino12 benzino12 is offline MS Project modify task - variable duration Windows 10 MS Project modify task - variable duration Office 2019
Novice
MS Project modify task - variable duration
 
Join Date: Mar 2023
Posts: 2
benzino12 is on a distinguished road
Default MS Project modify task - variable duration

Hey,



im new to this forum so please excuse if my questions already been asked..


Q1: How can i connect the start and the finish of a task with another one?
I want task 2 to always have the same dates than task 1...


Q2: I want to set the date of task 2 to a specific date and want to connect the finish to another task - for example - task 2 start at 1.1.2023 - finish at the end of task 1 - is that possible? Duration should be variable...


Thank you!!
Reply With Quote
  #2  
Old 03-30-2023, 09:27 AM
ProjectPlanner's Avatar
ProjectPlanner ProjectPlanner is offline MS Project modify task - variable duration Windows 10 MS Project modify task - variable duration Office 2019
Advanced Beginner
 
Join Date: Mar 2021
Location: UK
Posts: 72
ProjectPlanner is on a distinguished road
Default

I think you want to create a Hammock task. This video might help you.

https://youtu.be/2SC-W5Cvnrc
Reply With Quote
  #3  
Old 03-31-2023, 01:46 AM
benzino12 benzino12 is offline MS Project modify task - variable duration Windows 10 MS Project modify task - variable duration Office 2019
Novice
MS Project modify task - variable duration
 
Join Date: Mar 2023
Posts: 2
benzino12 is on a distinguished road
Default

yes!! Thank you!!
Reply With Quote
Reply

Tags
date, duration, task

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
How to modify the Gantt chart bar styles (label of values) in project center (WPA) (MS Project 2010) Cedahlia Project 0 04-21-2018 10:29 PM
MS Project modify task - variable duration Project Summary Task Duration incorrect BarryB Project 3 08-31-2016 02:43 AM
MS Project modify task - variable duration Fixed end but variable start (and duration) meileetan Project 3 08-22-2014 06:54 AM
MS Project modify task - variable duration Mid-Task resource scheduled 0 hours increasing task duration needlessly DarlaWeber Project 1 01-31-2014 02:30 PM
MS Project modify task - variable duration Linking task duration to another task branchi Project 1 08-15-2013 06:03 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:35 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft