hi everyone, i am new to the forum.
I have a question (maybe obvious to you!)
if for a task I have 100 hours available but for this project I can dedicate only 20% of the resource how do I get the correct task duration?
Reply With Quote
  #2  
Old 04-26-2023, 10:23 AM
DaleHowardMVP DaleHowardMVP is online now task duration Windows 10 task duration Office 2021
Advanced Beginner
 
Join Date: Apr 2023
Posts: 49
DaleHowardMVP is on a distinguished road
Default

The overall Duration of the project would be around 62.5 days, depending on your company holidays. What you need to do is to create your task list using Auto Scheduled tasks, leave the Duration of each task at the default Duration of 1 day, and then set task dependencies on every task in the project. Next, apply the Resource Sheet view and enter the names of your project team members. These steps are absolutely MANDATORY.

After doing this, apply the Gantt Chart view and then right-click anywhere in the white part of the Gantt Chart screen and select the Show Split item. This will apply the Task Entry view with the Gantt Chart view in the top pane and the Task Form view in the bottom pane. In the Gantt Chart pane, select the first task. In the Task Form pane, select the name of each resource you want to assign to the task, set their Units value to 20%, and then enter how many hours of Work each resource will perform on the task. When finished, click the OK button in the Task Form pane and Microsoft Project will calculate the Duration of that task for you. Repeat this process for every task in the project.

Hope this helps.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Physical % Complete and Task Duration ChuckM Project 3 02-09-2014 09:21 AM
task duration Mid-Task resource scheduled 0 hours increasing task duration needlessly DarlaWeber Project 1 01-31-2014 02:30 PM
Floating task duration dbsoccer Project 5 10-31-2013 09:10 AM
task duration Linking task duration to another task branchi Project 1 08-15-2013 06:03 AM
Task duration between 2 fixed milestones cettolox Project 3 01-24-2012 06:33 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:34 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft