#1
|
|||
|
|||
Multi-day holidays
Hello,
I am trying to enter a multi-day holiday in MS Project. In this case, it's Easter Friday & Monday, plus I will add the Tuesday as several people take that day off as well. I have gone to Project menu > Change working time > Exceptions and entered the Friday as the start date, and the Tuesday as the end date. However, the Gantt chart only shows the Friday as non-working. Going back to Exceptions, Project has changed the end date to the Friday; that is, the same as the start date. Is this a bug, or is there some trick involved? Thanks for any help. Project Online Desktop Client MSO version 2208 build 16.0.15601.20446 64-bit |
#2
|
|||
|
|||
Not sure why Microsoft Project is acting up on you. Why don't you just enter each day individually as nonworking time?
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Calendar for holidays | glda19 | Excel Programming | 5 | 11-04-2016 02:26 PM |
Legal Holidays | WildBill | Outlook | 0 | 08-06-2013 06:49 AM |
account for official holidays | ketanco | Project | 1 | 02-07-2013 07:51 AM |
New calendar in Outlook, no holidays | Dirtnapepr | Outlook | 2 | 09-15-2010 06:07 AM |
Holidays--clear all? | markg2 | Outlook | 0 | 11-01-2009 05:57 AM |