Task only on 2nd Thursday
 
Join Date: Jan 2023
Posts: 1
apeabo91 is on a distinguished road
Default Task only on 2nd Thursday


I have a task (Meeting B) that can only occur on the 2nd Thursday of each month. Additionally, it can only take place after Meeting A and Meeting A MUST be held at least 45 days before Meeting B.

I can't figure out how to get Project to constrain Meeting B to only the 2nd Thursday of each Month and 45 days after Meeting A. Thoughts?
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
ms project 2019 - network diagram - link (arrow) from summary task to task wongpmw Project 1 05-28-2022 04:57 AM
Insert Summary Task and Subsisting Task to Create A Consolidated Plan Lola_Amusa Project 1 04-27-2022 10:24 AM
Competing a task in Outlook does not automtically complete the linked task in OneNote OneGoat OneNote 0 06-22-2017 05:55 AM
On Thursday I had all of my quickparts in Outlook 2013 on Friday they were gone johngies Outlook 0 03-12-2017 10:18 AM
Task only on 2nd Thursday Copy and Paste of a Task...Including all of the Task's 'children'...to a new task KRTSTARRYNIGHT Project 1 07-01-2014 06:54 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:01 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft