#1
|
|||
|
|||
![]()
So I have tasks that have a certain length of time from start to finish - I want to add a milestone date in there (in this case, "Go-Live" that would show as a symbol on the existing task bar - without having to create a separate task for every single one of these.
Can this be done, and if so, I think I'm missing the "how" - seems like such a simple ask, but am not finding it. Would be very helpful to have that visually shown in the gantt bars. |
#2
|
||||
|
||||
![]()
Where will the milestone date come from? Would you enter it manually? If yes, here is a video of a solution using custom field
https://youtu.be/-hg6rajjhO8 Last edited by ProjectPlanner; 11-27-2022 at 10:31 AM. Reason: added solution |
#3
|
|||
|
|||
![]()
If your milestone date is the start or finish of a task, you could format the bar to show the date on the bar.
Apart from that, without resorting to VB (which MIGHT do it), then no. Its not a simple ask, in reality, as MSP shows a task per line, and a milestone is a separate task, so you would be trying to put two items into one line. |
#4
|
||||
|
||||
![]()
Yes, it's possible without VBA using custom field for milestone date.
![]() |
![]() |
Thread Tools | |
Display Modes | |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Project Summary Task formula to show milestone progress | joday48 | Project | 1 | 01-21-2022 10:35 AM |
Date format for task end/milestone in diagram | f_m | Project | 5 | 03-16-2020 03:37 AM |
![]() |
eNGiNe | PowerPoint | 6 | 05-27-2015 05:39 AM |
How to make a task adjust its end date depending on another task? (Newbie) | ravl13 | Project | 3 | 07-27-2014 06:10 PM |
Task with Start date but no Due date? | bplat | Outlook | 0 | 01-12-2012 08:10 AM |