HoneyBadger HoneyBadger is offline Can you add a Milestone (date) on an existing task? Windows 10 Can you add a Milestone (date) on an existing task? Office 2019
Novice
Can you add a Milestone (date) on an existing task?
 
Join Date: Nov 2022
Posts: 1
HoneyBadger is on a distinguished road
Default Can you add a Milestone (date) on an existing task?

So I have tasks that have a certain length of time from start to finish - I want to add a milestone date in there (in this case, "Go-Live" that would show as a symbol on the existing task bar - without having to create a separate task for every single one of these.




Can this be done, and if so, I think I'm missing the "how" - seems like such a simple ask, but am not finding it. Would be very helpful to have that visually shown in the gantt bars.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Project Summary Task formula to show milestone progress joday48 Project 1 01-21-2022 10:35 AM
Date format for task end/milestone in diagram f_m Project 5 03-16-2020 03:37 AM
Can you add a Milestone (date) on an existing task? edit date in footer of existing slides eNGiNe PowerPoint 6 05-27-2015 05:39 AM
How to make a task adjust its end date depending on another task? (Newbie) ravl13 Project 3 07-27-2014 06:10 PM
Task with Start date but no Due date? bplat Outlook 0 01-12-2012 08:10 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:09 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft