Creating a custom field for tables in reports, showing the hours/week of a task
Hi everyone, I'm working on some rapports and I would like to have a row that indicates the hour per week.
For example, The duration of a task might be 2 weeks, and the work might be 40 hours, I would like the custom field to calculate a simple divying up of the work effort, per week, in this case it would be 20 hrs per week. If it was 5 weeks and 50 hours, it would show as 10 hours a week. From there it should be easy to get it into a table row, showing it per task as a list. It's quite likely this must be possible using the custom field programming right? I've been having a look at it but I can't figure it out myself. Any help would be tremendously appreciated. |
Thread Tools | |
Display Modes | |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
3 Week Look Ahead-Custom Field/View | naparkins1 | Project | 0 | 05-08-2020 12:00 PM |
Creating report showing only part of work from one resource at a task with more resources working at | daniwei | Project | 2 | 06-24-2018 03:05 PM |
Creating 2 percentage fields to show the progress from week to week | Loay harhash | Project | 0 | 04-03-2018 03:26 AM |
Resource Reports not showing Sub project Resource group hours | RichB | Project | 3 | 02-24-2017 08:55 AM |
Custom field formula not working at summary task level | abw1987 | Project | 3 | 10-05-2011 07:17 AM |