#2
|
||||
|
||||
|
Select the Task you want to change resource profile for and then change your view to Task Usage. Now double-click the resource you want to apply a curve to and this will open the Assignment Information dialog.
Under the General tab, change the Work contour from Flat to Front Loaded =jerome PlannersPlace.com |
|
|