How to create teams (with both material and work) of resources and assign those teams in tasks?
Is there a way to group a number of resources and then assign this group to a task which will then have assigned several resources of one group in one click?
For example: Painting on walls: PAINTER[2]; PAINTER EQUIPMENT; SCAFFOLDS; BRUSHES; PAINTER ASSISTANT Then in MS Project I select only "Painting on walls", and this resources are assigned to the task? Obs. The end goal is to determine a Resource group productivity (such as 100m2/day) and when I assign this resource group with a quantity of m2 in a task, it will assign these resources and calculate the duration necessary to conclude the task. One way I think I would benefit a lot is if i could use the description in a custom lookup column, in this way I create a list of Teams and in the description I write for example "PAINTER[2]; PAINTER EQUIPMENT", then if I select a team and i can use the description i would need simply to put the description in the resource column, then the productivity would be a latter problem. Thank you |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Help! Using bookmark hyperlinks does not work correctly in word documents which are in teams/sharepo | Valeinsinööri | Word | 1 | 03-06-2022 05:43 PM |
Microsoft Teams - help for job interview! | isd1 | Misc | 1 | 10-22-2020 01:50 AM |
MS Teams | PuterSaurus | Office | 0 | 08-17-2018 10:33 AM |
Resource allocation for teams | Richard N | Project | 1 | 11-28-2016 02:33 PM |
Schedule deviation based on teams | csokosdama | Project | 1 | 03-03-2015 08:24 AM |