Resources and Fixed Work
I have a task with 3 resources assign like so.. Engineering. baseline work .3h Test baseline work 1h Assembly baseline work 5h The actual work was only performed by assembly at 3h and now the task is 100% complete. How do I get the task to show 100% complete without filling in actual work for engineering and test? |
|