Resources and Fixed Work
 
Join Date: Nov 2021
Posts: 46
JHalter is on a distinguished road
Default Resources and Fixed Work

I have a task with 3 resources assign like so..
Engineering. baseline work .3h
Test baseline work 1h
Assembly baseline work 5h



The actual work was only performed by assembly at 3h and now the task is 100% complete. How do I get the task to show 100% complete without filling in actual work for engineering and test?
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
How to create a Man Hour Resource with fixed durations and fixed Work jayreb31 Project 0 07-03-2019 01:14 PM
Fixing Work, % of actual work and Final Date in a task (while assigning resources) Campelliann Project 1 01-09-2017 06:15 PM
Resources and Fixed Work Auto-level resources for parallel tasks with fixed work cineasta Project 5 11-21-2013 01:03 PM
Resources and Fixed Work Fixed duration, fixed units, fixed work, effort driven. How, why and when use it all Evgeny Project 3 01-03-2013 06:45 AM
Resources and Fixed Work How to use fixed duration, fixed work and have resources/units leveled automatically? Joeb Project 3 06-25-2012 04:18 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 08:37 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft