#1
|
|||
|
|||
Summary Task Name in formula
Hello, I would like to display inside the gantt bars, the name of the task (easy) and the name of the summary task. As I will have a lot of repetitive tasks, with the only difference will be the summary/group task, I would like to be able to see this difference on the gantt chart. I already tried by creating a custom field, with formula but then I'm not able to get the Summarry task name in my formula. I would like to have something as the following idea, but [SummaryTaskName] doesn't exist. IIf([Summary]=Yes;"";[SummaryTaskName] & " - " & [Name]) Can someone help me ? How to retrieve the summary task name in a formula ? Thanks for your help |
#2
|
||||
|
||||
Just enter the formula [Name] in your custom field and make sure that you tick the "Use Formula" radio button under "Calculation for task and group summary rows".
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
ms project 2019 - network diagram - link (arrow) from summary task to task | wongpmw | Project | 1 | 05-28-2022 04:57 AM |
Insert Summary Task and Subsisting Task to Create A Consolidated Plan | Lola_Amusa | Project | 1 | 04-27-2022 10:24 AM |
Project Summary Task formula to show milestone progress | joday48 | Project | 1 | 01-21-2022 10:35 AM |
Rollup Summary Tasks to Project Summary Task | shep555 | Project | 1 | 05-24-2014 12:28 PM |
Custom field formula not working at summary task level | abw1987 | Project | 3 | 10-05-2011 07:17 AM |