Iain L. Iain L. is offline Adjust a linked task duration when Predecessor and Successors change Windows 10 Adjust a linked task duration when Predecessor and Successors change Office 2019
Novice
Adjust a linked task duration when Predecessor and Successors change
 
Join Date: Apr 2022
Posts: 1
Iain L. is on a distinguished road
Default Adjust a linked task duration when Predecessor and Successors change


Hi,
I would like to know if it is possible to automatically adjust the duration of a task if its predecessor and or Successor change. For instance I have to hire a vessel to load out some equipment and maintain the vessel on site to return the equipment. If the tasks the equipment is required for take longer (or shorter) than originally planned then the duration of the hire of the vessel will change. In excel it is easy as the the duration can be simply calculated by subtracting the finish date and time for the end of the voyage to port from the initial mobilization date. At present the duration does change only the start or finish date when changing FS, SS,SF, etc.
Reply With Quote
  #2  
Old 04-05-2022, 11:19 AM
ProjectPlanner's Avatar
ProjectPlanner ProjectPlanner is offline Adjust a linked task duration when Predecessor and Successors change Windows 10 Adjust a linked task duration when Predecessor and Successors change Office 2019
Advanced Beginner
 
Join Date: Mar 2021
Location: UK
Posts: 72
ProjectPlanner is on a distinguished road
Default

Make your Lorry Hire Task a Hammock.

To create a hammock, copy the start date of the first Task that uses the equipment and use Paste Special >> Paste Link, to paste in the start date field of the Lorry Hire Task.

Similarly, copy the finish date of the last Task that uses the equipment and use Paste Special >> Paste Link, to paste in the finish date field of the Lorry Hire Task.

Your Lorry Hire Task should now be dynamically linked to equipment use and a change in equipment use Tasks duration will also change Lorry Hire duration. You can confirm Lorry Hire is dynamically linked as there should be a small black triangle at the bottom right corner of the Start & Finish dates.

Planners' Place
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Competing a task in Outlook does not automtically complete the linked task in OneNote OneGoat OneNote 0 06-22-2017 05:55 AM
How to make a task adjust its end date depending on another task? (Newbie) ravl13 Project 3 07-27-2014 06:10 PM
Adjust a linked task duration when Predecessor and Successors change Mid-Task resource scheduled 0 hours increasing task duration needlessly DarlaWeber Project 1 01-31-2014 02:30 PM
Adjust a linked task duration when Predecessor and Successors change Linking task duration to another task branchi Project 1 08-15-2013 06:03 AM
Adjust a linked task duration when Predecessor and Successors change arrows remain between task bars, but predecessor info disappears from task info Antares Project 1 12-14-2011 09:19 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 07:07 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft