Adjust a linked task duration when Predecessor and Successors change
Hi,
I would like to know if it is possible to automatically adjust the duration of a task if its predecessor and or Successor change. For instance I have to hire a vessel to load out some equipment and maintain the vessel on site to return the equipment. If the tasks the equipment is required for take longer (or shorter) than originally planned then the duration of the hire of the vessel will change. In excel it is easy as the the duration can be simply calculated by subtracting the finish date and time for the end of the voyage to port from the initial mobilization date. At present the duration does change only the start or finish date when changing FS, SS,SF, etc. |
#2
|
||||
|
||||
Make your Lorry Hire Task a Hammock.
To create a hammock, copy the start date of the first Task that uses the equipment and use Paste Special >> Paste Link, to paste in the start date field of the Lorry Hire Task. Similarly, copy the finish date of the last Task that uses the equipment and use Paste Special >> Paste Link, to paste in the finish date field of the Lorry Hire Task. Your Lorry Hire Task should now be dynamically linked to equipment use and a change in equipment use Tasks duration will also change Lorry Hire duration. You can confirm Lorry Hire is dynamically linked as there should be a small black triangle at the bottom right corner of the Start & Finish dates. Planners' Place |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Competing a task in Outlook does not automtically complete the linked task in OneNote | OneGoat | OneNote | 0 | 06-22-2017 05:55 AM |
How to make a task adjust its end date depending on another task? (Newbie) | ravl13 | Project | 3 | 07-27-2014 06:10 PM |
Mid-Task resource scheduled 0 hours increasing task duration needlessly | DarlaWeber | Project | 1 | 01-31-2014 02:30 PM |
Linking task duration to another task | branchi | Project | 1 | 08-15-2013 06:03 AM |
arrows remain between task bars, but predecessor info disappears from task info | Antares | Project | 1 | 12-14-2011 09:19 AM |