Hey

Probably a question asked may times... Im not looking for this by task, just a single Actual vs scheduled % value that i can deliver to my management team as this is the main question to me...

so, i need to get the following values

1. the percentage through the scheduled project. If it was a 100 day project and im current 50 days in, this value would be 50%

2. the percentage of actual completed work. If it was a 100 day project, im at 50 days but have completed 65 days work, the value would (50%) 65%

3. the percentage ahead of actual completed work. If it was a 100 day project, im 65%, 15% over the schedule, the value would be 15% ahead

I can do a report, i'd like to know if


  • Project can already provide these values
  • What fields would i need to calculate to do this myself



Thanks
Reply With Quote
  #2  
Old 03-18-2022, 09:06 PM
ProjectPlanner's Avatar
ProjectPlanner ProjectPlanner is offline Project Progress - Actual vs Estimated Windows 10 Project Progress - Actual vs Estimated Office 2019
Advanced Beginner
 
Join Date: Mar 2021
Location: UK
Posts: 72
ProjectPlanner is on a distinguished road
Default

I might be wrong but I think you need to calculate Scheduled % (Baseline %) for tasks to get the overall value.

This video might help you. Also read the pinned comment as it improves the formula in the video when an error occurs.

https://youtu.be/egWA82E1i1w
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Project Summary Task formula to show milestone progress joday48 Project 1 01-21-2022 10:35 AM
Actual hours Excel to Project JHalter Project 0 12-06-2021 03:43 PM
Trying to show Actual v. Estimated Progress LVanpelt Project 0 05-03-2018 01:48 PM
Project Progress - Actual vs Estimated Need totoal cost despite project being in progress Sognamed Project 1 07-23-2013 06:06 AM
MS Project able to import actual start and or actual finish date from Excel? mhacker Project 0 04-26-2010 11:29 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 10:05 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft