Hi,



I have a set of recurring tasks that cover a five year period. Some of the tasks are legislative deadlines that are absolute final dates. Currently Project will choose the first working day following (i.e. the next Monday).

How do I set Project to choose the first working day before this cut off, and not the first working day after?

regards
Guy
Reply With Quote
  #2  
Old 09-25-2010, 07:57 AM
Kimberly Kimberly is offline Recurring tasks falling on weekends - programme for working day prior Windows 7 Recurring tasks falling on weekends - programme for working day prior Office 2010 (Version 14.0)
Expert
 
Join Date: May 2010
Posts: 517
Kimberly is on a distinguished road
Default

What technique did you use to create the deadline dates for the recurring tasks? (Project uses the day following what date?)
Reply With Quote
  #3  
Old 09-26-2010, 03:21 PM
guyc guyc is offline Recurring tasks falling on weekends - programme for working day prior Windows XP Recurring tasks falling on weekends - programme for working day prior Office 2007
Novice
Recurring tasks falling on weekends - programme for working day prior
 
Join Date: Jun 2010
Posts: 3
guyc is on a distinguished road
Default

Actually, your question may have provided the answer I need. I'll check it out.

To answer you, I didn't set a deadline, I set up a date for the task to recur on, based on a Government programme here in NZ. However, when I set that up I did not return to it and make it into a deadline. I'll try that and see what happens.

kind regards
Guy C
Reply With Quote
  #4  
Old 09-26-2010, 03:32 PM
guyc guyc is offline Recurring tasks falling on weekends - programme for working day prior Windows XP Recurring tasks falling on weekends - programme for working day prior Office 2007
Novice
Recurring tasks falling on weekends - programme for working day prior
 
Join Date: Jun 2010
Posts: 3
guyc is on a distinguished road
Default

Followup - yes, it was the deadline issue. The Default was set to "Start no earlier than" rather than "Must finish on".

Thanks for the direction to head in!

gc
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
filtering recurring task pascal Project 0 05-05-2010 08:07 AM
Recurring tasks falling on weekends - programme for working day prior Delay/Pause animated photo prior to next clipart BettyC PowerPoint 2 04-19-2010 02:12 PM
Recurring Outline Slide daviddoria PowerPoint 0 10-24-2009 09:06 AM
Stop Future Recurring Meetings mileskb Outlook 0 06-03-2009 04:59 AM
Archiving recurring meetings grfxdesigner Outlook 0 03-26-2009 03:43 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 07:54 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft