Old 01-20-2022, 04:06 AM
joday48 joday48 is offline Project Summary Task formula to show milestone progress Windows 7 64bit Project Summary Task formula to show milestone progress Office 2010 32bit
Novice
Project Summary Task formula to show milestone progress
 
Join Date: Jun 2012
Posts: 24
joday48 is on a distinguished road
Default Project Summary Task formula to show milestone progress

I have a client who is struggling to understand why milestones progress is not reflected in the project summary task. I have a schedule structured as follows:

-Build milestones
-Design milestones
-Production tasks (fixed work, all resourced).

Is there a formula (or some other way) that I can use to reflect the progress of the milestones at summary task level?

I have attached a couple of snap shots of my schedule if that is helpful.



Thank you
Attached Images
File Type: png Summary.PNG (275.9 KB, 9 views)
File Type: png Production.PNG (267.8 KB, 9 views)
Reply With Quote
  #2  
Old 01-21-2022, 10:35 AM
ProjectPlanner's Avatar
ProjectPlanner ProjectPlanner is offline Project Summary Task formula to show milestone progress Windows 10 Project Summary Task formula to show milestone progress Office 2019
Advanced Beginner
 
Join Date: Mar 2021
Location: UK
Posts: 72
ProjectPlanner is on a distinguished road
Default

Try following the steps in the video on calculating summary progress when are subtasks are milestones.

How to calculate summary task percent complete when all subtasks are milestones in Microsoft Project - YouTube
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Project Summary Task formula to show milestone progress Project Summary Task Percent Complete round with no decimals advillanuevag Project 4 04-19-2021 11:52 AM
How to calculate summary progress date time on summary tasks Logotip Project 0 05-16-2017 01:18 AM
Project Summary Task formula to show milestone progress Project Summary Task Duration incorrect BarryB Project 3 08-31-2016 02:43 AM
Rollup Summary Tasks to Project Summary Task shep555 Project 1 05-24-2014 12:28 PM
Project Summary Task formula to show milestone progress summary task calculating from project start ketanco Project 1 01-02-2012 02:34 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 05:43 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft