#1
|
|||
|
|||
Finish Date not calculated correctly
I have one task that starts on 8/1/22 and ends on 1/23/23, but the duration is 2.5 days. The end date isn't calculating correctly.
I have theses resources assigned to the task, total 27.2 baseline work hours... EE... 20h ME... .4h TE-E... 1.2h MA... 5.6h How do I get the finish date corrected? |
#2
|
|||
|
|||
Put task in auto schedule mode
Is the task in auto-schedule mode? This has happened to me before and this worked.
|
#3
|
|||
|
|||
Yes it is auto scheduled. I was able to figure it out by moving resources around.
Thanks! |
Thread Tools | |
Display Modes | |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Making product labels with auto calculated expiration date | adrianppa | Word | 2 | 04-07-2017 12:46 AM |
% completion changes finish date? | Puddlerunna | Project | 9 | 11-25-2014 06:16 AM |
what to put in to schedule for dealing with overall finish date | ketanco | Project | 7 | 10-30-2014 02:25 PM |
flag to indicate finish date does not equal baseline finish date | TCB | Project | 3 | 08-06-2014 02:49 PM |
Inserting a date calculated from a table cell | theMikeD | Word | 2 | 09-11-2012 05:46 PM |