1. Yes, Summary Tasks are also sorted
2. In the schedule you attached, Urbanisation has date of June 2022 while Phase 1 Building Construction has date of October 2021, therefore Urbanisation should appear last.

Reply With Quote
 

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Task View Filter problem martinkoenig Outlook 0 01-26-2018 12:00 PM
Problem with View>Sort... Mail Merge View problem drgt Mail Merge 2 02-14-2017 04:31 AM
Excel sort problem jaz Excel 2 01-16-2011 04:24 AM
Problem with View>Sort... Sort problem Cpat Excel 1 09-19-2010 03:08 AM
MS Outlook 2002 Address Book Sort Problem.... blizzster Outlook 0 07-30-2009 07:52 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:27 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft