Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 10-01-2021, 04:09 AM
Ilya Vychuzhanin Ilya Vychuzhanin is offline Earned Value isn't recalculated by MS Project Windows 10 Earned Value isn't recalculated by MS Project Office 2019
Novice
Earned Value isn't recalculated by MS Project
 
Join Date: Oct 2021
Posts: 1
Ilya Vychuzhanin is on a distinguished road
Default Earned Value isn't recalculated by MS Project

Dear experts,



I can't solve such problem. I want to import from Excel such data: "physical % complete" and "actual work" to update Earned value (BCWP) and ACWP.

I import only 3 fields: Task ID (task ID is used as a merge key to merge the data from Excel to Project), "physical % complete" and "actual work".

Problem occurs when data is imported. "Physical % complete" and "actual work" fields are filled with excel data, ACWP field is recalculated according to new "actual work" data from Excel, but BCWP turns to 0. When write the same "Physical % complete" in the corresponding cells manually, the BCWP is recalculated as it should be.

What is the problem with importing "Physical % complete" and recalculating BCWP, how to solve it???

Bellow is attached 3 screenshots:
1. Initial data in project
2. Excel data was imported ("Physical % complete", "actual work" and ACWP have been updated, BCWP turned to 0)
3. I just manually entered the same imported data over imported cells and BCWP recalculated)

Updated "Physical % complete", "actual work" data is highlighted in yellow.


Initial project data.jpg

Excel data is imported.jpg

Data is written manualy.jpg
Reply With Quote
  #2  
Old 10-01-2021, 10:53 AM
ProjectPlanner's Avatar
ProjectPlanner ProjectPlanner is offline Earned Value isn't recalculated by MS Project Windows 10 Earned Value isn't recalculated by MS Project Office 2019
Advanced Beginner
 
Join Date: Mar 2021
Location: UK
Posts: 72
ProjectPlanner is on a distinguished road
Default

Ilya,

I also encountered the same problem when I replicated the physical % import either through Excel or XML.

Unfortunately, I don't know what is causing it but a workaround is to add a new Cost custom field, say Cost1 & rename it Calculated BCWP and enter the following formula.

[Baseline Cost]*[Physical % Complete]/100

and for "calculation for task and group summary rows", select Rollup: Sum.

Hide the default BCWP and display the Calculated BCWP field and it will work with both Excel import and manual update.

=jerome
Reply With Quote
  #3  
Old 10-02-2021, 08:28 AM
Guloluseus Guloluseus is offline Earned Value isn't recalculated by MS Project Windows 7 64bit Earned Value isn't recalculated by MS Project Office 2010 32bit
Competent Performer
 
Join Date: Mar 2013
Posts: 168
Guloluseus is on a distinguished road
Default

The problem is that ACWP isnt calculated by Project- it is the actual cost. You would need to add the "actual cost" column to the programme and fill it on. BCWP is based on the %age complete to findo ut what it should cost, whereas actual cost can be any number.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Earned Value Calculations - BCWP In Microsoft Project Lenin Project 0 03-25-2016 09:20 AM
Earned Value isn't recalculated by MS Project Microsoft Project Managing Planned / Earned Value & Actual Costs shane_dav71 Project 1 10-06-2014 06:07 PM
Earned Value isn't recalculated by MS Project MS Project not calculating earned value correctly mtbtomo Project 1 10-23-2013 06:49 AM
Finding Earned Values for Different Baselines in a single project pratik6312 Project 1 08-22-2013 11:18 AM
earned value not calculating ketanco Project 3 08-16-2012 02:13 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:10 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft