How is total duration calculated and what causes the variation between duration & total duration
 
Join Date: Jul 2021
Posts: 1
rvp is on a distinguished road
Exclamation How is total duration calculated and what causes the variation between duration & total duration

I am fairly new to MS projects and after preparing a project plan, I was asked why was there a duration between the 2 fields i.e Duration & Total duration.


I initially assumed that the total duration field is a rolling calendar day sum but I dont think that is the case.

At a high level, my project plan has a duration of 225 days where as total duration is at 864 days.

Also This varies across the different indent tasks. Some the former is higher than the latter and its the opposite in some cases.

Please help understand what going on
Attached Images
File Type: png Screen Shot 2021-07-14 at 2.08.16 PM.png (34.1 KB, 10 views)
Reply With Quote
  #2  
Old 07-17-2021, 09:26 PM
ProjectPlanner's Avatar
ProjectPlanner ProjectPlanner is offline How is total duration calculated and what causes the variation between duration & total duration Windows 10 How is total duration calculated and what causes the variation between duration & total duration Office 2019
Advanced Beginner
 
Join Date: Mar 2021
Location: UK
Posts: 72
ProjectPlanner is on a distinguished road
Default

Your "Duration" field calculates the difference between Start & Finish dates, while your "Total Duration" field sums up the duration of sub-tasks under a Summary task.

Did you inherit the schedule? Just curious as to why you would add a field to the schedule if you don't know what it does.

BTW, I want to believe your "Total Duration" is a custom field and not a default Microsoft Project field as it is not listed in the list of duration fields. Duration fields - Project

Last edited by ProjectPlanner; 07-17-2021 at 09:27 PM. Reason: edited for clarity
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
How is total duration calculated and what causes the variation between duration & total duration Want to total duration and date to 1st floor Glewis Project 1 05-10-2015 02:51 PM
% complete by duration ketanco Project 5 10-01-2014 07:35 AM
wav duration during slideshow jalea148 PowerPoint 2 06-30-2014 11:39 PM
How is total duration calculated and what causes the variation between duration & total duration total slack not changing when changing duration ketanco Project 1 02-11-2012 07:23 AM
How is total duration calculated and what causes the variation between duration & total duration calculating duration ketanco Project 5 12-15-2011 07:15 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 05:15 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft