In case of multiple resources, how can I only level individual resources
Dear MS Project professionals,
In would like to do an analysis on my plan. For this analysis I would like to level only 2 of my 10 resources. Is it possible to process that kind of resource leveling? If yes: How? The reason for this approach is, that the other 8 resources can easily be levelled manually and I want to level them afterwards. Thank you very much in advance. |
#2
|
|||
|
|||
go to resource utilisation and select the resource(s) you want to level on and level the plan. When asked agree that you only want to level for the selected resources
|
Tags |
leveling, resources |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Level Resources | k.noseworthy | Project | 1 | 04-11-2019 04:46 AM |
Creating task lists for individual resources | Jack91 | Project | 1 | 02-23-2015 07:43 AM |
Resources - only allow users to select from resources pool | grazi | Project | 1 | 04-04-2014 11:12 AM |
Auto-level resources for parallel tasks with fixed work | cineasta | Project | 5 | 11-21-2013 01:03 PM |
Multiple resources | Tedzer | Project | 1 | 11-12-2013 08:02 AM |