miless2111s miless2111s is offline In case of multiple resources, how can I only level individual resources Windows 7 32bit In case of multiple resources, how can I only level individual resources Office 2007
Advanced Beginner
 
Join Date: May 2016
Posts: 32
miless2111s is on a distinguished road
Default

go to resource utilisation and select the resource(s) you want to level on and level the plan. When asked agree that you only want to level for the selected resources
Reply With Quote
 

Tags
leveling, resources



Similar Threads
Thread Thread Starter Forum Replies Last Post
Level Resources k.noseworthy Project 1 04-11-2019 04:46 AM
Creating task lists for individual resources Jack91 Project 1 02-23-2015 07:43 AM
In case of multiple resources, how can I only level individual resources Resources - only allow users to select from resources pool grazi Project 1 04-04-2014 11:12 AM
In case of multiple resources, how can I only level individual resources Auto-level resources for parallel tasks with fixed work cineasta Project 5 11-21-2013 01:03 PM
Multiple resources Tedzer Project 1 11-12-2013 08:02 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 08:20 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft