Hi all

I have:


- many tasks and among them one task T1 which starts on 07/01 and end on 09/30
- many resources and among them one resource "John"

"John" can only work on T1 on those time slots:
- from 07/10 to 07/20
- from 08/15 to 08/30

I would like to assign John to the task T1 only the given periods.

Does anyone have any idea how to do that with Project?
The only thing I found is the "Resource usage" panel and the possibility to enter a fix duration for the resource on the task.
I was not able to enter different time slots for the resource

Any help would be appreciated
Thanks
Reply With Quote
  #2  
Old 10-23-2021, 07:06 PM
minerva.goree minerva.goree is offline Assign a resource to a same task with many time slot Windows 10 Assign a resource to a same task with many time slot Office 2019
Novice
 
Join Date: Oct 2021
Posts: 6
minerva.goree is on a distinguished road
Default

You can use the Task Usage view and assign hours to John in the time-phased section during the dates indicated.

Attached is an example image of the Task Usage view (well I customized my view with the colors).
Attached Images
File Type: jpg Project Task Usage View and hours spread.jpg (72.3 KB, 11 views)
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Automatically assign first available resource of a certain type yolevins Project 0 03-03-2021 01:14 AM
Resource leveling part time resource smachin1000 Project 2 09-07-2017 06:45 AM
Assign a resource to a same task with many time slot how to assign a labor resource more than once ketanco Project 3 02-11-2014 12:23 PM
Assign a resource to a same task with many time slot Mid-Task resource scheduled 0 hours increasing task duration needlessly DarlaWeber Project 1 01-31-2014 02:30 PM
Assign a resource to a same task with many time slot Assign resource groups to tasks jjmclell Project 2 12-17-2012 04:28 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 05:17 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft