Assign a resource to a same task with many time slot
Hi all
I have: - many tasks and among them one task T1 which starts on 07/01 and end on 09/30 - many resources and among them one resource "John" "John" can only work on T1 on those time slots: - from 07/10 to 07/20 - from 08/15 to 08/30 I would like to assign John to the task T1 only the given periods. Does anyone have any idea how to do that with Project? The only thing I found is the "Resource usage" panel and the possibility to enter a fix duration for the resource on the task. I was not able to enter different time slots for the resource Any help would be appreciated Thanks |
#2
|
|||
|
|||
You can use the Task Usage view and assign hours to John in the time-phased section during the dates indicated.
Attached is an example image of the Task Usage view (well I customized my view with the colors). |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Automatically assign first available resource of a certain type | yolevins | Project | 0 | 03-03-2021 01:14 AM |
Resource leveling part time resource | smachin1000 | Project | 2 | 09-07-2017 06:45 AM |
how to assign a labor resource more than once | ketanco | Project | 3 | 02-11-2014 12:23 PM |
Mid-Task resource scheduled 0 hours increasing task duration needlessly | DarlaWeber | Project | 1 | 01-31-2014 02:30 PM |
Assign resource groups to tasks | jjmclell | Project | 2 | 12-17-2012 04:28 AM |