Old 10-23-2021, 07:06 PM
minerva.goree minerva.goree is offline Assign a resource to a same task with many time slot Windows 10 Assign a resource to a same task with many time slot Office 2019
Novice
 
Join Date: Oct 2021
Posts: 6
minerva.goree is on a distinguished road
Default

You can use the Task Usage view and assign hours to John in the time-phased section during the dates indicated.

Attached is an example image of the Task Usage view (well I customized my view with the colors).
Attached Images
File Type: jpg Project Task Usage View and hours spread.jpg (72.3 KB, 13 views)
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Automatically assign first available resource of a certain type yolevins Project 0 03-03-2021 01:14 AM
Resource leveling part time resource smachin1000 Project 2 09-07-2017 06:45 AM
Assign a resource to a same task with many time slot how to assign a labor resource more than once ketanco Project 3 02-11-2014 12:23 PM
Assign a resource to a same task with many time slot Mid-Task resource scheduled 0 hours increasing task duration needlessly DarlaWeber Project 1 01-31-2014 02:30 PM
Assign a resource to a same task with many time slot Assign resource groups to tasks jjmclell Project 2 12-17-2012 04:28 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 10:47 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft