seanpears99 seanpears99 is offline Burndown chart tasks missing Windows 7 64bit Burndown chart tasks missing Office 2007
Novice
Burndown chart tasks missing
 
Join Date: Oct 2011
Posts: 12
seanpears99 is on a distinguished road
Default Burndown chart tasks missing

Hi all

I have searched for something similar and couldnt find anything.

We have a burndown chart attached to a cutover schedule but after a certain date remaining and remaining baseline tasks drop off rapidly, yet there are tasks in the schedule with remaining work and nothing has been assigned to a different sprint.

Im not crash hot on Burndowns, but can anyone explain where I would need to look to see why there is a drastic reduction?

TIA


Sean
Attached Images
File Type: png burndown.PNG (28.1 KB, 9 views)
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Org Chart Name field missing after import pbassett Visio 1 01-01-2018 12:52 PM
Burndown chart tasks missing Problem with Burndown Chart CSR Project 1 07-15-2016 05:21 PM
Burndown chart tasks missing Gantt chart - reverse tasks dependency dnantia Project 11 01-16-2016 07:31 PM
Burndown chart tasks missing Missing Tasks from Network Diagram View OTPM Project 3 11-20-2012 03:37 PM
Showing unscheduled tasks on Gantt chart jaworski_m Project 0 11-20-2011 12:37 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 07:49 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft