herodot herodot is offline Auto Leveling Resources in MS Project Windows 10 Auto Leveling Resources in MS Project Office 2016
Novice
Auto Leveling Resources in MS Project
 
Join Date: Jun 2020
Posts: 12
herodot is on a distinguished road
Default Auto Leveling Resources in MS Project

Hello!

Let's say I have 2 activities with a fixed duration (4days).

A1 - Day1 to Day 4
A2 - Day1 to Day 4


Worker1 is set to work at both activities at the same time.
Microsoft Project will tell me that we have a problem, because the Worker1 is working 200%.

My question: There is a (automate) way to split the working time of Worker1 so that the over allocation will disappear.



I would like to distribute the working time of my worker evenly to my activities. = He will work 2 days to Activity1 and 2 days to Activity2.

Any hidden feature of M Project to do this without trying to tackle this information manually?
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Auto Leveling Resources in MS Project Leveling of resources ignores milestone links gharli Project 1 11-29-2015 11:50 AM
Auto Leveling Resources in MS Project Leveling Resources Help! Mthomas88 Project 1 09-25-2015 08:25 AM
Auto Leveling Resources in MS Project Certain Resources Not Leveling PDX-ADM-TRM01 Project 1 04-27-2015 03:45 PM
Question about leveling a project..... sssb2000 Project 3 02-05-2015 12:11 PM
Auto Leveling Resources in MS Project resource leveling in ms project ketanco Project 1 12-24-2011 12:58 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:34 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft