Hi guys,

recently I added a custom field in my Project Schedule to show % complete with decimals, thanks to Jerome´s reply to a previous thread I posted in the forum.

Now I am using the same custom field to show %complete with decimals, but I notice that when I have a summary task that contains only milestones (activities with a duration of zero days), when I update the % complete to one or some of the milestones within that summary task, the summary task remains showing 0%, unless I give 100% compete to all of its subtasks.

Is there any way for a Summary task that contains only milestones to summarize the total % complete when some of its milestones reach 100%?
Attached Images
File Type: png Summary.png (11.8 KB, 12 views)
Reply With Quote
  #2  
Old 06-12-2021, 03:51 PM
ProjectPlanner's Avatar
ProjectPlanner ProjectPlanner is offline Summary task does not summarize % complete Windows 10 Summary task does not summarize % complete Office 2019
Advanced Beginner
 
Join Date: Mar 2021
Location: UK
Posts: 72
ProjectPlanner is on a distinguished road
Default

I've produced a workaround using 4 custom number fields as helper columns and 1 custom text field to hold a custom "Task %".

The YouTube video for this workaround is at How to calculate summary task percent complete when all subtasks are milestones in Microsoft Project - YouTube
Reply With Quote
  #3  
Old 06-12-2021, 06:22 PM
advillanuevag advillanuevag is offline Summary task does not summarize % complete Windows 10 Summary task does not summarize % complete Office 2019
Novice
Summary task does not summarize % complete
 
Join Date: Apr 2021
Posts: 12
advillanuevag is on a distinguished road
Default Thank you Jerome!

I just saw your youtube video, and it is the perfect solution I was needing to make Microsoft Project show summary % complete for a summary task containing only milestones as sub-tasks with some of them 100% completed.

Thank you for taking the time to create a solution for that issue.

Regards,

Alberto.
Reply With Quote
Reply

Tags
percent complete, summary tasks



Similar Threads
Thread Thread Starter Forum Replies Last Post
Summary task does not summarize % complete Project Summary Task Percent Complete round with no decimals advillanuevag Project 4 04-19-2021 11:52 AM
% Complete for Summary Task not Calculating? lynn0712 Project 0 12-20-2018 09:41 AM
Summary task does not summarize % complete Showing how much work is required to complete a project according to summary task start/end times PDX-ADM-TRM01 Project 1 03-30-2015 04:05 PM
Rollup Summary Tasks to Project Summary Task shep555 Project 1 05-24-2014 12:28 PM
Summary task does not summarize % complete Summarize durations by top level task tcdoha Project 1 01-10-2013 11:24 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 11:32 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft