Hi guys,

recently I added a custom field in my Project Schedule to show % complete with decimals, thanks to Jerome´s reply to a previous thread I posted in the forum.

Now I am using the same custom field to show %complete with decimals, but I notice that when I have a summary task that contains only milestones (activities with a duration of zero days), when I update the % complete to one or some of the milestones within that summary task, the summary task remains showing 0%, unless I give 100% compete to all of its subtasks.

Is there any way for a Summary task that contains only milestones to summarize the total % complete when some of its milestones reach 100%?
Attached Images
File Type: png Summary.png (11.8 KB, 12 views)
Reply With Quote
  #2  
Old 06-12-2021, 03:51 PM
ProjectPlanner's Avatar
ProjectPlanner ProjectPlanner is offline Summary task does not summarize % complete Windows 10 Summary task does not summarize % complete Office 2019
Advanced Beginner
 
Join Date: Mar 2021
Location: UK
Posts: 72
ProjectPlanner is on a distinguished road
Default

I've produced a workaround using 4 custom number fields as helper columns and 1 custom text field to hold a custom "Task %".

The YouTube video for this workaround is at How to calculate summary task percent complete when all subtasks are milestones in Microsoft Project - YouTube
Reply With Quote
  #3  
Old 06-12-2021, 06:22 PM
advillanuevag advillanuevag is offline Summary task does not summarize % complete Windows 10 Summary task does not summarize % complete Office 2019
Novice
Summary task does not summarize % complete
 
Join Date: Apr 2021
Posts: 12
advillanuevag is on a distinguished road
Default Thank you Jerome!

I just saw your youtube video, and it is the perfect solution I was needing to make Microsoft Project show summary % complete for a summary task containing only milestones as sub-tasks with some of them 100% completed.

Thank you for taking the time to create a solution for that issue.

Regards,

Alberto.
Reply With Quote
Reply

Tags
percent complete, summary tasks

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Summary task does not summarize % complete Project Summary Task Percent Complete round with no decimals advillanuevag Project 4 04-19-2021 11:52 AM
% Complete for Summary Task not Calculating? lynn0712 Project 0 12-20-2018 09:41 AM
Summary task does not summarize % complete Showing how much work is required to complete a project according to summary task start/end times PDX-ADM-TRM01 Project 1 03-30-2015 04:05 PM
Rollup Summary Tasks to Project Summary Task shep555 Project 1 05-24-2014 12:28 PM
Summary task does not summarize % complete Summarize durations by top level task tcdoha Project 1 01-10-2013 11:24 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 07:27 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft